Please be advised that beginning on Monday, June 27, 2016, the milling and paving project will commence in the Goettens Area neighborhood to complete the project area as originally proposed. The following street segments will be resurfaced:
• 12th Street South from Cooper Avenue South to 13th Street South
• 13th Street South from Patricia Drive to 525 feet east
• 13th Street South from 25th Avenue South to Maine Prairie Road
• 14th Street South from Cooper Avenue South to Prairie Hill Road
• 16th Street South from Goettens Way to Oak Grove Road SW
• 17th Street South from Patricia Drive to Goettens Way
Through traffic will be maintained, but motorists can expect major traffic delays and are advised to find an alternate route if possible.
Please note that minor utility work may begin the week of June 20th. It is anticipated that this mill and overlay project will be completed by the end of July 2016.